| $100,000
RECORD OF THE PROCEEDINGS
SKAGIT COUNTY BOARD OF COMMISSIONERS
MONDAY, APRIL 4, 2005
PAGE NO. 2
2. Miscellaneous.
a) Public Works Engineer
Steve Flude reported that the Guemes Ferry has been out of service since
the middle of last week and is currently dry-docked at Dakota Creek. Repairs
are going well and the ferry should be back in service on Wednesday, April
6, 2005. The total cost of repairs, drydocking, staff time and private
carriers to transport passengers will be approximately $100,000.
Mr. Flude advised
that because of the interruption to ferry service, the expiration date
for the frequent user's ticket books would be extended.
|