What Did the Haul Out Cost? $1,276,965.71

The Guemes Island Ferry went into dry dock on September 12, 2005 to have the bottom painted, new engines installed, and ADA and sponson modifications to the vessel made. More than four weeks were added to the outage in October/November with the ferry returning to service on November 12. Repair work was done on the Anacortes dock and begun on the Guemes dock. While in dry dock, one repaired outdrive was installed and the second outdrive repaired. New controls were installed along with extensive rewiring. Engine housings were enlarged to accommodate the new engines.

An oil leak in one newly repaired outdrive was discovered during initial test runs, necessitating additional dry docking and repair at the Dakota Creek Shipyard.

Throughout the haulout, van service was provided on Guemes Island and Arrow Launch ran both beach landing and ramp docking passenger vessels.

What did all this cost? Considerably more than the $800,000 originally budgeted. It has been a very expensive year for the ferry with parking lot work, multiple breakdowns and the loss of revenue during outages.

Contract No.
Contractor
Description
Cost
C20040290 Elliot Bay Design Vessel modifications design
$79,400.00
C20050178 Arrow Launch Passenger service
$210,000.00
C20050304 Cummins Engines and reduction gears
$355,584.45
C20050382 Puglia Engineering, Inc. Dry dock work
$359,805.46
C20050385 Culbertson Dock bearing repair
$25,214.00
C20050398 Culbertson *Sidewalk relocation
$85,766.84
C20050430 Puglia Engineering, Inc **Additional work not covered in original contract
$99,757.10
C20050451 Puglia Engineering, Inc **Additional work not covered in original contract
$11,928.40
C20050481 Puglia Engineering, Inc **Additional work not covered in original contract
$6,871.00
C20050507 Down Under Guemes Ramp clearing
$2,600.39
  Van service drivers Guemes shuttle service
$24,926.71
  Van rental  
$516.00
  Dakota Creek Dry dock/repairs
$13,991.20
  Garbage service  
***$604.16
   

*Yet to be completed.

**Change orders [860k PDF]

***Includes billing of $266.66 which may not be paid.

As of 12.15.05, $971,814.21 has been invoiced and paid toward these contracts by Skagit County.


$1,276,965.71


Source: Skagit County records and Skagit County Public Works