What
Did the Haul Out Cost? $1,276,965.71
The Guemes Island
Ferry went into dry dock on September 12, 2005 to have the bottom painted,
new engines installed, and ADA and sponson modifications to the vessel
made. More than four weeks were added to the outage in October/November
with the ferry returning to service on November 12. Repair work was done
on the Anacortes dock and begun on the Guemes dock. While in dry dock,
one repaired outdrive was installed and the second outdrive repaired.
New controls were installed along with extensive rewiring. Engine housings
were enlarged to accommodate the new engines.
An oil leak in
one newly repaired outdrive was discovered during initial test runs, necessitating
additional dry docking and repair at the Dakota Creek Shipyard.
Throughout the
haulout, van service was provided on Guemes Island and Arrow Launch ran
both beach landing and ramp docking passenger vessels.
What did all this
cost? Considerably more than the $800,000 originally budgeted. It has
been a very expensive year for the ferry with parking lot work, multiple
breakdowns and the loss of revenue during outages. |
Contract
No.
|
Contractor
|
Description
|
Cost
|
| C20040290 |
Elliot
Bay Design |
Vessel
modifications design |
$79,400.00 |
| C20050178 |
Arrow
Launch |
Passenger
service |
$210,000.00 |
| C20050304 |
Cummins |
Engines
and reduction gears |
$355,584.45 |
| C20050382 |
Puglia
Engineering, Inc. |
Dry dock
work |
$359,805.46 |
| C20050385
|
Culbertson |
Dock bearing
repair |
$25,214.00 |
| C20050398 |
Culbertson |
*Sidewalk
relocation |
$85,766.84 |
| C20050430 |
Puglia
Engineering, Inc |
**Additional
work not covered in original contract |
$99,757.10 |
| C20050451 |
Puglia
Engineering, Inc |
**Additional
work not covered in original contract |
$11,928.40 |
| C20050481 |
Puglia
Engineering, Inc |
**Additional
work not covered in original contract |
$6,871.00 |
| C20050507 |
Down Under
Guemes |
Ramp clearing |
$2,600.39 |
| |
Van service
drivers |
Guemes
shuttle service |
$24,926.71 |
| |
Van rental |
|
$516.00 |
| |
Dakota
Creek |
Dry dock/repairs |
$13,991.20 |
| |
Garbage
service |
|
***$604.16 |
| |
|
*Yet to be completed.
**Change
orders [860k PDF]
***Includes billing
of $266.66 which may not be paid.
As of 12.15.05, $971,814.21
has been invoiced and paid toward these contracts by Skagit County.
|
$1,276,965.71 |
Source: Skagit County
records and Skagit County Public Works
|
|