Proposed
Water Pipeline To Guemes Island
Skagit County
Public Utility District submitted a grant application to the State of
Washington for $1,000,000 towards a $2,000,000 pipeline to carry water
under Guemes channel from Anacortes. Now, according to Greg Peterka, engineering
manager, the PUD will "cancel the Anacortes-Guemes transmission line
grant application with DOH [Department of Health]! (not a misprint or
humor). The pipeline idea is over".
LineTime sent
the following questions to the Skagit PUD, as well as a request for a
statement explaining the proposal and its subsequent withdrawal.
|
LineTime
|
Greg
Peterka, Engineering Manager for Skagit PUD
|
| Where
did the idea for the project originate? |
The
Anacortes/Guemes source (waterline) concept has been discussed in the
past whenever discussions involve long term water solutions for Guemes
Island. Discussion first took place in the late 1990’s when the
District reviewed a list of options for serving water to the Potlatch
community that was under order to abandon their wells due to seawater
intrusion.
This list of options
was assembled by a consultant from Whatcom County. It included the Anacortes-Guemes
pipeline as one option, but that option was considered to be too costly
to pursue. |
| Who
made the decision to file the grant proposal? |
Greg
Peterka, Engineering Manager for Skagit PUD, submitted the grant application.
Due to the approaching
deadline the application was submitted to the State without detailed engineering
or discussion. It was completed in about five hours. The District first
heard of this funding source approximately two weeks before the submittal
deadline. The Guemes Island application was completed and submitted to
the State on the deadline date.
A short time prior
to that, the District submitted two other applications for unrelated water
projects for other community water systems.
|
| Who
are the intended beneficiaries of this project? |
Since
the pipeline on the island would be extended over time, the present and
future property owners on Guemes Island would be the primary beneficiaries
of this project.
Fire protection would
be available on the island as the water system developed. |
| Who
would benefit financially from the project? |
Primarily,
those that are having well problems, those who may draw seawater into their
existing well, and those who would otherwise need to acquire a future drinking
water source without taking on the usual risks associated with drilling
for water. |
The
grant application is for $1 million for a $2 million project.
Where will the second million dollars come from? |
The
estimated cost for the project ($2 million) was selected to maximize the
net grant amount ($1 million).
The cost estimate
for this sort of project was based on estimates developed in the late
1990’s (upwards of
$450,000) and has not been recently updated or evaluated. It is the sort
of project that could cost even more due to permitting issues.
If the grant were
to be approved and accepted, there would need to be further research and
discussion before a plan for cost distribution could take place. As a
rule of thumb, the property owners benefiting from a project pay for their
share of the project costs, minus any portion for grants and other contributions. |
| How
many hookups are you planning for? Will hookups be mandatory or voluntary? |
The
eventual number of hookups was not explored.
History shows that the District has never forced a property owner to abandon
their private well to connect to a public system.
Other agencies such
as the Dept. of Ecology or Health could someday require connection to
a public system under unique circumstances. New building permits on the
island could someday be conditioned upon connecting to a public water
system, especially if the lot fronted on a public waterline. |
| Where
will the water come from? Does the City of Anacortes have sufficient capacity
and are they willing to guarantee water to us in perpetuity? |
The
water was to originate from the City of Anacortes water system which provides
filtered water from the Skagit River.
Capacity and other
issues were not investigated, but it was assumed that adequate arrangements
could be made with the City of Anacortes. Similar arrangements with the
City have taken place over the past 30 years on Fidalgo Island.
The water system for
the City of Anacortes is strong, reliable, and well run. |
| Is
this project subject to vote and, if yes, by whom? |
It
would be too early to determine who would vote and who would make the
decision to proceed to the next step of this concept, if any.
If the grant for this
project was rejected (likely in this case), no such questions would apply.
The application was submitted in hopes to highlight the pipeline project
in the minds of health officials, environmentalists, and those that would
benefit from it. |
| When
will the decision on the grant application be made? |
The
State indicated to the District that a “list” of projects may
be available by March of 2004. Since this application has been withdrawn,
it is no longer being considered for funding. |
| Additional
comments: |
The
District’s engineering department saw this project as a long term
engineering remedy for ongoing groundwater issues such as seawater intrusion
and existing, struggling community water systems that may someday ask
the District to become involved.
It is important to
understand that District policy makers are not comfortable with assuming
the responsibility of groundwater water systems (existing or future) on
a sensitive island such as Guemes. Sea water intrusion issues are a significant
concern for the District.
This grant application
was submitted in hopes to offer Guemes Island residents a future option
to solve the long term need for reliable drinking water.
Mr. Peterka regrets
having made the application on behalf of the Island, and he wishes the
best for the people of Guemes Island. |