| Progress
Report On Ferry Work
Attached are some
additional photographs of the GUEMES as of October 18, 2005.
The engines are in
place and deck painting is in progress to finish up the work on deck.
The engines and control system installation is progressing with little
or no problems. The equipment that we have been awaiting, driveline connections
are to be delivered this afternoon.
We will commence dock
trials on Monday, October 24th. Sea Trials will commence on Tuesday, October
25th. Crew training will start this Friday and continue thru the 25th
of October. It appears we are still on track for delivery of the ferry
on the 26th.
- Steve
Cox, Ferry Manager
[10.18.5]

|