Progress Report On Ferry Work


Attached are some additional photographs of the GUEMES as of October 18, 2005.

The engines are in place and deck painting is in progress to finish up the work on deck. The engines and control system installation is progressing with little or no problems. The equipment that we have been awaiting, driveline connections are to be delivered this afternoon.

We will commence dock trials on Monday, October 24th. Sea Trials will commence on Tuesday, October 25th. Crew training will start this Friday and continue thru the 25th of October. It appears we are still on track for delivery of the ferry on the 26th.

- Steve Cox, Ferry Manager [10.18.5]